30 bay building for WM Morrison’s in Turriff

We were contacted by Malcolm in the middle of October to discuss options for a new socially distanced canteen for their staff at Woodhead’s site in Turriff.

Several emails and layouts were exchanged before the final layout of 30 modules were decided, 24 on the ground floor and 6 on the top.

With two sets of external stairs to create a one-way system.

Time was of the essence, the order was confirmed on 20th November and the building was delivered on 14th December.

The client provided a 150T crane for three days to site and stack the building, the fitters connected, sealed and trimmed the building in 7 days leaving the site on Monday 21st December.